Grant Progress Summary:
- 27 Grants Awarded between 2022 and 2026
- 38 Total Projects
- Over $98 million dollars worth of total project costs
- 18 Grants Completed as of Nov. 16, 2026
- 9 Remaining Grant Projects with varying deadlines, but they should all be complete by the end of 2028.
Overview
Grant acceptance means the City must:
(1) complete the projects
(2) as set forth in the applications
(3) following the specific grant guidelines and
(4) within the grant period of performance.
Otherwise, the City risks losing future grant opportunities.
Grant project workload since 2024 and grant deadlines have caused the timeline of other planned projects to be shifted as grant-funded projects take priority for on-time completion.
Most grant applications were for approved projects or projects that were set forth in the City's master plans. These master plans were built through citizen input and have been an important factor in Joplin’s successful grant awards.
Joplin’s past successful grant project performance and administration has been another important factor in the grants awarded.
- State, County and City ARPA awards had to be obligated by 12/31/2024: Joplin’s funds were properly obligated by this date.
- Any City ARPA funds not obligated by that date were required to be returned to U.S. Treasury.
- Now, the City is required to spend the funds as reported by 12/31/2026.
- City claimed $10 million revenue loss allowed under ARPA regulations.
- Remaining balance of $3,779,739 allocated to Broadband as set forth by ARPA regulations.
- Funds obligated by the City through the State and County are required to be spent as set forth by either 6/30/2026, 9/30/2026 or 12/31/2026, depending on the timelines set by the pass-through agency.
- Grant awarded following successful application.
- Complete any requirements for final grant award.
- Implement and execute grant projects based on award requirements within the performance period.
- Complete required grant reports and submit grant reimbursement requests.
| Grantor Agency | Grant | Project | Total Project Cost | Grant Amount Awarded | City Match Amount |
|---|---|---|---|---|---|
| HUD | Community Project Grant | Streetscape along Main Street from 8th to 15th Street | $6,000,000 | $3,000,000 | $3,000,000 |
State of MO ARPA | Justice Center Grant (Legislative Priority) | Justice Center Facility Improvements | $2,000,000 | $1,000,000 | $1,000,000 |
| State of MO ARPA | Drinking Water Grant (Legislative Priority) | Zora Street Water Main Install; County Road 180 Water Main; 7th Street Water Main Install | $10,000,000 | $5,000,000 | $-0- |
| State of MO ARPA | Stormwater Infrastructure Grant | Nine Total Project Sites | $8,676,000 | $5,000,000 | $3,676,000 |
| State of MO ARPA | Stormwater Infrastructure Grant | Nine Total Project Sites | $6,155,427 | $3,625,546 | $2,529,881 |
| State of MO ARPA | Wastewater Infrastructure Grant | 12th and Iowa Project | $5,266,782 | $3,599,782 | $1,667,000 |
| County ARPA | Jasper County | 20th Street Widening Project | $14,220,000 | $4,500,000 | $9,420,000 |
| County ARPA | Jasper County | MOSWIN Interoperability Radios | $637,048 | $637,048 | $-0- |
| State of MO | Governor's Transportation Cost-Share (MODOT) | Zora St Widening and Improvement Project | $10,754,000 | $4,000,000 | $6,454,000 |
| State of MO ARPA | Community Revitalization Grant | Neighborhood Improvement - Down Payment Assistance; Demolitions; and Home Rehabilitation & Repair | $7,000,000 | $7,000,000 | $-0- |
| State of MO ARPA | Emergency Medical Services Grant | Fire EMS Equipment | $41,894 | $41,894 | $-0- |
| State of MO ARPA | Fire Protection Grant Program | Fire 2nd Set of Turnout Gear | $54,594 | $54,594 | $-0- |
| State of MO ARPA | Peace Officer Grant Program | Police Body Cameras | $42,000 | $42,000 | $-0- |
| State of MO ARPA | Local Tourism Asset Development Grant | Dover Outdoor Recreation Area (DORA) MOmentum Bike Park | $6,774,507 | $4,008,280 | $2,766,227 |
| State Dept of Health ARPA | State and Local Cybersecurity Grant | Cybersecurity Resilience | $123,497 | $123,497 | $-0- |
| EPA BIL | Recycling Education and Outreach Grant (REO) | Joplin Regional Recycling Outreach | $2,355,244 | $1,740,000 | $615,244 |
| FTA BIL | Areas of Persistent Poverty (AoPP) | Implementation of a Sustainable Transit Program | $500,000 | $400,000 | $100,000 |
| FAA BIL/AIP | Federal Aviation Administration BIL and AIP Grant | Air Traffic Control Tower: (1) Equipment Replacement (2) Lighting and Control Management System | $1,060,310 | $1,050,295 | $10,015 |
| FAA BIL | Federal Aviation Administration BIL | Rehabilitate Taxiway E | $1,409,020 | $1,338,569 | $70,451 |
| City ARPA | City ARPA Grant | Citywide Broadband | $5,000,000 | $5,000,000 | $-0- |
| City ARPA | City ARPA Grant | Tin Cup Trail Bridge Connector | $1,665,698 | $750,000 | $915,698 |
| City ARPA | City ARPA Grant | MSSU Roy Blunt Health Science Innovation Center | $1,500,000 | $1,500,000 | $-0- |
| FHWA | Tap Grant | Grand Falls Trail | $1,396,005 | $600,000 | $796,005 |
| National Park Service | Outdoor Recreation Legacy Partnership (ORLP) | Improvements at Parr Hill Park | $968,460 | $484,230 | $484,230 |
| DNR BIL | Recreational Trails Program (RTP) | Trail Amenities across various City Parks | $245,350 | $147,210 | $98,140 |
| HUD | Lead Hazard Reduction | Lead Remediation for Residential Homes | $3,500,000 | $3,150,000 | $350,000 |
| LWCF | Land & Water Conservation Fund Grants | Dover Outdoor Recreation Area Trail Addition | $1,000,000 | $500,000 | $500,000 |
| GRAND TOTAL | $98,345,836 | $58,292,945 | $34,452,891 |
Project | Grant Amount Awarded | Amount Spent/Claimed to Date | Remaining Balance |
|---|---|---|---|
| Community Revitalization (State Grant Match Portion) | $3,500,000 | $3,500,000.00 | -0- |
| FireEMS Equipment (State Grant Match Portion) | $21,894 | $21,894 | -0- |
| Fire Equipment (State Grant Match Portion) | $34,594 | $34,594 | -0- |
| PoliceEquipment (State Grant Match Portion) | $22,000 | $22,000 | -0- |
| MSSU Health Science Innovation Center (State Grant Match Portion) | $1,500,000 | $1,500,000 | -0- |
| Dover Outdoor Recreation Area (DORA) (Grant Project Additional Amount) | $2,451,251 | $2,451,251 | -0- |
| Citywide Fiber Broadband Network | $5,000,000 | $5,000,000 | -0- |
| 20th Street Widening Project (Grant Project Additional Amount) | $500,000 | $500,000 | -0- |
| Tin Cup Trail Bridge Connector (Existing Project Additional Amount) | $750,000 | $750,000 | -0- |
| GRAND TOTAL | $13,779,739 | $13,779,739 | $-0- |
Projects In Progress: Detailed Status
| Project Name | Recycling Education and Outreach (REO) Grant |
|---|---|
| Total Project Cost | $2,355,244 |
| Grant Period of Performance | June 1, 2024 through May 31, 2027 |
| Anticipated Timeline | Consultant work began November 2024 Estimated Completion March 2027 |
| Project Description | This project will encourage the collection of recycled materials and (1) inform the public about community recycling programs; (2) provide information about the recycled materials that are accepted as part of a community recycling program that provides for the separate collection of residential solid waste from recycled material; and (3) increase collection rates and decrease contamination in community recycling programs. |
| Project Status Update | The City was assigned a project officer by the EPA for this grant. City staff completed the required paperwork to receive the final award. The final award was received with a grant start date of June 1. Consultant was hired and began work in November 2024. The grant will be completed in March of 2027. Marketing is underway. |
City Match from Solid Waste Fund: $615,244
+ Grant Award: $1,740,000
+ Other Funding: $0
= Total Project Cost: $2,355,244
| Project Name | Parr Hill Park Improvements Project |
|---|---|
| Total Project Cost | $968,460 |
| Grant Period of Performance | 10/1/2025 through 10/31/2027 |
| Anticipated Timeline | Project was fully awarded in October of 2025. Project is underway. |
| Project Description | This project will improve Parr Hill Park. Two new all-inclusive playgrounds with pour-in-play surfacing will be relocated and installed. Outdoor fitness equipment will be added along the trail throughout the park. Permanent outdoor games will be included. Additional sidewalks will be installed to ensure connective ADA accessibility. Finally, the basketball court will be overlaid and transitioned to a multi-sport court. |
| Project Status Update | Project is underway with an anticipated completion date of Summer/early Fall 2027. |
City Match from Parks/Stormwater Sales Tax: $484,230
+ Grant Award: $484,230
+ Other Funding: $0
= Total Project Cost: $968,460
| Project Name | Trail Amenities Project |
|---|---|
| Total Project Cost | $245,350 |
| Grant Period of Performance | 11/1/2024 through 11/30/2027 |
| Anticipated Timeline | NEPA work finalized and final notice to proceed was just received. Bids will be sent for review by DNR. It is anticipated this project will start early 2027. |
| Project Description | This project provides trail amenities across twelve (12) various park locations. Specifically, the project consists of the installation of eighty (80) 6-foot ADA compliant park benches, forty-eight (48) bicycle racks and eight (8) bicycle repair stations, as well as twenty-one (21) trail/park trailway signs along eighteen (18) miles of public trails. The parks include Cunningham Park, Mercy Park, Wildcat Park, McIndoe Park, Tin Cup Trail, Grand Falls Trail, Landreth Park, Parr Hill Park, Senator Ron Richard Memorial Park, Humphrey Park, Leonard Park, and Mohaska Park. |
| Project Status Update | •Final notice to proceed just issued. •Bid package will be sent to DNR for approval. •Construction will begin early 2027 and will be complete Fall of 2027. |
City Match from Parks/Stormwater Sales Tax: $98,140
+ Grant Award: $147,210
+ City ARPA Funding: $0
= Total Project Cost: $245,350
| Project Name | Dover Outdoor Recreation Area Trail Addition (LWCF) |
|---|---|
| Total Project Cost | $1,000,000 |
| Grant Period of Performance | 10/1/2026 through 10/31/2028 |
| Anticipated Timeline | RFQ for design will be issued in November. Design must be complete within first six months of award. Construction will begin in 2027. |
| Project Description | This project includes the construction of a 2/3rd multi-use trail that will span from the trailhead on Murphy Boulevard and run along Joplin Creek to the trailhead at Lone Elm Road. The trail will be a 12’ wide asphalt trail and will include an 11’ wide pre-formed pedestrian bridge across Joplin Creek. Wayfinding signage will be placed along the trail and the trailheads. |
| Project Status Update | •RFQ for design will be issued in November of 2026. Design will be complete by March 30, 2027. •Construction will begin in 2027. |
City Match from Parks/Stormwater Sales Tax: $500,000
+ Grant Award: $500,000
+ City ARPA Funding: $0
= Total Project Cost: $1,000,000
| Project Name | Lead Hazard Remediation for Residential Homes Project |
|---|---|
| Total Project Cost | $3,500,000 |
| Grant Period of Performance | 6/1/2025 through 6/1/2029 |
| Anticipated Timeline | This project is underway. Marketing is underway to attract applicants. |
| Project Description | This project will help prevent lead poisoning among very-low and low-income families with young children by removing lead-based paint hazards from their homes. It is anticipated the funding will help address 75-150 housing units across the City. Activities conducted under this grant can include: • Lead-based paint inspection and risk assessment • New windows, doors, siding, trim, exterior & interior painting, porch repair and home safety measures (if identified as a lead or healthy homes hazard) • Targeted Outreach, education and training |
| Project Status Update | • This project has begun. • Marketing is underway to attract applicants. • Work will begin as applicants are approved. • This grant ends on 6/1/29. |
City Match from General Fund Use Tax: $350,000
+ Grant Award: $3,150,000
+ City ARPA Funding: $0
= Total Project Cost: $3,500,000
| Project Name | Streetscape along Main Street from 8th to 15th Street |
|---|---|
| Total Project Cost | $6,000,000 |
| Grant Period of Performance | August 31, 2030 |
| Anticipated Timeline | Construction has begun. Estimated Completion Fall 2027 |
| Project Description | Streetscape from 8th to 15th Street along Main Street, to include some side streets depending on bid prices and available funding. Beautification at 10th and Main Street is separately funded but is part of this overall project on a similar timeline. |
| Project Status Update | Design is complete. Public meeting has been held. Project was bid and construction contract was awarded by City Council. Construction has begun. It is estimated the project will require one year for construction. |
City Match from Transportation Sales Tax: $3,000,000
+ Grant Award: $3,000,000
+ Other Funding Source: $0
= Total Project Cost: $6,000,000
| Project Name | Zora Street Widening and Improvement Project |
|---|---|
| Total Project Cost | $10,754,000 |
| Grant Period of Performance | Governor’s Grant receives extensions |
| Anticipated Timeline | Anticipated Construction beginning Fall 2024 Estimated Completion December 2027 |
| Project Description | This project consists of improving Zora Street from Rangeline Road nearly to Highway 249. It is broken into three phases. The first phase is improving the intersection at Zora and Duquesne Roads. The second phase is improving Zora Street from Duquesne Road nearly to Highway 249. The third phase is improving Zora Street from just east of Rangeline Road to Duquesne Road. • |
| Project Status Update | Phase three is about 95% designed with right-of-way acquisition in process. Phase one is complete. Phase two is nearing completion. The final phase is expected to be bid December 2027, with construction to begin in the Spring of 2027. The estimated completion for the entire project is December of 2027. |
City Match from CIST Fund: $6,454,000
+ Grant Award: $4,000,000
+ Other Funding Source (City of Webb City): $300,000
= Total Project Cost: $10,754,000
| Project Name | Areas of Persistent Poverty (AOPP) Grant – Sustainable Structure Transit Study |
|---|---|
| Total Project Cost | $500,000 |
| Grant Period of Performance | TBD |
| Anticipated Timeline | Consultant has been hired Estimated Completion: Current phases are complete. Evaluating any additional work with remaining balance. |
| Project Description | As a community priority, this project will commission a feasibility assessment that will evaluate local public transportation and recommend feasible options that promote more ridership in areas considered historically disadvantaged communities or designated as areas of persistent poverty. Specifically, the study will define methods of how the City of Joplin can financially support the expansion of its transit system to areas where there is a need for more affordable access to employment, public services, education, and healthcare facilities. |
| Project Status Update | The City completed the required paperwork to receive the final award. Consultant has been hired. Current phases are complete. Final plan was presented to City Council in January of 2026. Phase II has been completed. An evaluation of any additional work needed with remaining grant balance. |
City Match from Transportation Sales Tax: $100,000
+ Grant Award: $400,000
+ Other Funding: $0
= Total Project Cost: $500,000
| Project Name | Grand Falls Trail Project (TAP Grant) |
|---|---|
| Total Project Cost | $1,396,005 |
| Grant Period of Performance | TBD |
| Anticipated Timeline | Trail is anticipated to be bid by end of this year. Estimated Completion Summer 2027. |
| Project Description | This project will construct a 1.2 mile hard-surfaced ADA hiking/walking/nature/biking trail along scenic Grand Falls. This project involves the construction of a new 12’ wide paved, non-motorized trail. |
| Project Status Update | •Paperwork is underway with MoDOT. •Trail Design is complete. Overlook design is complete. •It is anticipated trail construction will begin Winter of 2027. The trail is expected to be complete by the Summer of 2027. |
City Match from Parks/Stormwater Sales Tax: $796,005
+ Grant Award: $600,000
+ Other Funding: $0
= Total Project Cost: $1,396,005
Completed Projects: Detail
| Project Name | Stormwater Infrastructure Grant |
|---|---|
| Total Project Cost | $14,831,427 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by August 31, 2026 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project consists of the following nine stormwater projects: •17th & Annie Baxter (Removed) East Town (Complete) •9th & St Louis (Complete) 12th & Wall (Complete) •Massachusetts & Murphy Blvd (Complete) 5th & Porter (Complete) •Ten Pin Lane (Complete) Texas Avenue 11th to 15th •26th St Twin Culverts (Complete) (Complete) • |
| Project Status Update | PROJECT IS COMPLETE! |
City Match from Parks/Stormwater Sales Tax: $6,205,881
+ Grant Award: $8,625,546
+ Other Funding: $0
= Total Project Cost: $14,831,427
| Project Name | 20th Street Widening Project |
|---|---|
| Total Project Cost | $14,220,000 |
| Grant Period of Performance | Must be under contract by December 31, 2024; ARPA Funds must be complete by September 30, 2026 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project consists of designing the widening of 20th Street from Schifferdecker to State Line Road and construction of the widening of 20th Street from Schifferdecker to Central City Road. This widening will be designed as a complete street with a separated and designated pedestrian and bicycle path. |
| Project Status Update | •This project is properly obligated. •Contract has been awarded; Right-of-Way and Utility relocation underway. •Construction began April 7, 2025. Roundabout is complete. The estimated completion of the Eastern and Western portions and the Central City Roundabout is September 2026. PROJECT IS COMPLETE! |
City Match from CIST Fund: $9,420,000
+ Grant Award/Other Funding: $4,300,000
+ City ARPA Funding: $500,000
= Total Project Cost: $14,220,000
| Project Name | Community Revitalization Grant |
| Total Project Cost | $7,000,000 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by June 30, 2026 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project begins to address much of the neighborhood revitalization action plans through three programs: •Downpayment and closing cost assistance – No more than 20% of the purchase price not to exceed $40,000 per applicant, based on income guidelines for primary residence inside city limits of Joplin. 116 Homes. •Home Repairs and Rehabilitation – Maximum award is $25,000 per household for minor exterior repairs such as roof, siding, windows, HVAC, sidewalks, etc. within the 4 Qualified Census Tracts. 90 Homes. •Demolitions – Follow existing dangerous building process, within the 4 Qualified Census Tracts, no duplication of benefits. 46 Demolished, Former Freeman Building Demolished |
| Project Status Update | •Project is properly obligated. •Downpayment and closing cost assistance complete. Demolitions are underway. Home Repair and Rehabilitation Program is underway. •Project is Complete! |
City Match: $0
+ Grant Award: $3,500,000
+ City ARPA Funding: $3,500,000
= Total Project Cost: $7,000,000
| Project Name | Citywide Broadband Fiber Project |
|---|---|
| Total Project Cost | $5,000,000 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by December 31, 2026 |
| Anticipated Timeline | Anticipated Construction beginning Fall of 2024 City Portion is Complete! |
| Project Description | This project will bring access to fiber broadband access to the entire community. |
| Project Status Update |
|
City Match: $0
+ Grant Award: $0
+ City ARPA Funding: $5,000,000
= Total Project Cost: $5,000,000
| Project Name | Tin Cup Trail Bridge Connector Project |
|---|---|
| Total Project Cost | $1,665,698 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by December 31, 2026 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project will construct a bridge as a connector for the Tin Cup Trail in conjunction with construction of both phases of the Tin Cup Trail. |
| Project Status Update | •This project is properly obligated. •Contract has been awarded. •Project is Complete! |
City Match from Transportation Use Tax: $915,698
+ Grant Award: $0
+ City ARPA Funding: $750,000
= Total Project Cost: $1,665,698
| Project Name | Justice Center Facility Improvements |
|---|---|
| Total Project Cost | $2,000,000 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by June 30, 2026 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project consists of the following improvements and updates to the Justice Center: •Electrical Distribution Equip Sub-Panel Replacement •Main Distr Switchboard Basement Roof Restoration •Motor Control Center Window Replacement •Domestic Water Distribution Sidewalk Replacement •Chilled Water Chillers Duct Work Cleaning |
| Project Status Update | •Project has been expanded to utilize the full funding. •Project is properly obligated. •Project is complete! |
City Match from Public Safety Sales Tax: $1,000,000
+ Grant Award: $1,000,000
+ Other Funding Source: $0
= Total Project Cost: $2,000,000
| Project Name | Drinking Water Main Extensions |
|---|---|
| Total Project Cost | $10,000,000 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by September 30, 2026 |
| Anticipated Timeline | Project is Complete! |
| Project Description | This project consists of the following water line extensions: •Zora Street Water Main Installation – Install 10,000’ of 12” water main along Zora Street from east of Duquesne Road to east of Highway 249 •County Road 180 Water Main Installation – Install 9,000’ of 12” water main along County Road 180, north of Apple Road •7th Street Water Main Installation – Install 6,400’ of 12” water main along 7th Street from Duquesne Road to Kinser Road |
| Project Status Update | •Project is properly obligated. •Project is being expanded due to favorable bids. •Project is Complete! |
City Match: $0 (N/A)
+ Grant Award: $5,000,000
+ Missouri American Water Funding: $5,000,000
= Total Project Cost: $10,000,000
| Project Name | Wastewater Infrastructure Grant |
|---|---|
| Total Project Cost | $5,266,782 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by August 31, 2026 |
| Anticipated Timeline | Project is Complete! |
| Project Description | This project consists of sewer improvements in the 12th & Iowa area. |
| Project Status Update | •Project is properly obligated. •Construction is underway. •Project is Complete! |
City Match from Sewer Fund: $1,667,000
+ Grant Award: $3,599,782
+ Other Funding: $0
= Total Project Cost: $5,266,782
| Project Name | MOSWIN Interoperability Radio Project |
|---|---|
| Total Project Cost | $637,048 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by December 31, 2026 |
| Anticipated Timeline | Project is Complete! |
| Project Description | This project provides the system that will allow the Police Department to communicate by radio to public safety agencies across the State of Missouri. |
| Project Status Update | This project is part of the JASCO MOSWIN conversion project. All Edge equipment has been received. Additional channel has been added at South Site. Subscriber equipment has been shipped. Required paperwork has been submitted to the State Radio System Administration. All equipment is installed and connected to MOSWIN. Project is complete! |
City Match: $0 (N/A)
+ Grant Award: $637,048
+ Other Funding: $0
= Total Project Cost: $637,048
| Project Name | Fire EMS Equipment Project |
|---|---|
| Total Project Cost | $41,894 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by June 30, 2026 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project is for EMS equipment and training equipment. Specifically, the following items: •Case Review Monitoring Software Pediatric Trainer •Video Laryngoscope Adult Trainer •Laryngoscope Blades EZ IO Supplies |
| Project Status Update | •Project is properly obligated. •The equipment has been purchased, received and is in service. •Project closeout is complete. |
City Match: $0 (N/A)
+ Grant Award: $20,000
+ City ARPA Funding: $21,894
= Total Project Cost: $41,894
| Project Name | Fire Protection Equipment Grant |
|---|---|
| Total Project Cost | $54,594 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by June 30, 2026 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project is for the purchase of 21 sets of turnout gear to begin to provide our firefighters with a second set of turnout gear. |
| Project Status Update | •Project is properly obligated. •Twenty-One sets of turnout gear have been purchased and put in service. •Project closeout is complete.
|
City Match: $0 (N/A)
+ Grant Award: $637,048
+ Other Funding: $0
= Total Project Cost: $637,048
| Project Name | Police Officer Equipment Grant |
|---|---|
| Total Project Cost | $42,000 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by June 30, 2026 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project is for the purchase of 20 body cameras for Sergeants and above to ensure all police personnel are properly equipped. |
| Project Status Update | •Project is properly obligated. •The equipment has been purchased, received, and is in service. •Project closeout is complete. |
City Match: $0 (N/A)
+ Grant Award: $20,000
+ City ARPA Funding: $22,000
= Total Project Cost: $42,000
| Project Name | Local Tourism Asset Development Grant (Dover Outdoor Recreation Area -DORA) Momentum Bike Park |
|---|---|
| Total Project Cost | $6,774,507 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by June 30, 2026 |
| Anticipated Timeline | Project is Complete! |
| Project Description | This project consists of constructing an outdoor bicycle recreation area, including bicycle trails, a pump track, a children’s bicycle playground, a restroom, shelter and parking areas to be a regional tourism draw. |
| Project Status Update | •Project has been properly obligated. •Project is Complete! |
City Match from Parks/Stormwater Sales Tax Fund and CVB Fund: $2,766,227
+ Grant Award: $1,557,029
+ City ARPA Funding: $2,451,251
= Total Project Cost: $6,774,507
| Project Name | Cybersecurity Grant |
|---|---|
| Total Project Cost | $123,497 |
| Grant Period of Performance | July 31, 2025 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project enhances cybersecurity resilience. It includes the purchase of laptops for training purposes and for areas where certain employees lack access to a daily computer. It also includes domain MFA (multi-factor authentication) and a sandbox server to further enhance cybersecurity efforts. Finally, this grant will cover in-person training for city employees. |
| Project Status Update | This project is underway. The laptops are purchased, configured and installed. The sandbox server is built, configured and in our environment. Project is Complete! |
City Match: $0 (N/A)
+ Grant Award: $123,497
+ Other Funding: $0
= Total Project Cost: $123,497
| Project Name | Air Traffic Control Tower Project |
|---|---|
| Total Project Cost | $1,060,310 |
| Grant Period of Performance | August 2027 |
| Anticipated Timeline | PROJECT IS COMPLETE! |
| Project Description | This project consists of two Air Traffic Control Tower Projects covered mostly by a BIL grant, with the remainder covered by the AIP grant. The first project is for equipment replacement at the ATCT to include tower radios, voice control system, ATIS weather equipment, etc. The second project is for an airport lighting and control management system to remotely control the airport lighting from the tower. This system will be much more reliable through fiber optic cable. |
| Project Status Update | This project is complete. |
City Match from Airport Fund: $10,015
+ Grant Award: $1,050,295
+ Other Funding: $0
= Total Project Cost: $1,060,310
| Project Name | Rehabilitate Taxiway E Project |
|---|---|
| Total Project Cost | $1,409,020 |
| Grant Period of Performance | August 2027 |
| Anticipated Timeline | Project is Complete! |
| Project Description | This project consists of the rehabilitation of Taxiway E as part of the Runway 13/31 Rehabilitation Project. |
| Project Status Update | Project is Complete! |
City Match from Airport Fund: $70,451
+ Grant Award: $1,338,569
+ Other Funding: $0
= Total Project Cost: $1,409,020
| Project Name | MSSU Roy Blunt Health Science Innovation Center Project |
|---|---|
| Total Project Cost | $1,500,000 |
| Grant Period of Performance | Must be under contract by December 31, 2024; Project must be complete by December 31, 2026 |
| Anticipated Timeline | Project is Complete! |
| Project Description | This project will construct a new Health Science Innovation Center on the campus of MSSU. |
| Project Status Update | Project is complete! |
City Match: $0 (N/A)
+ Grant Award: $0
+ City ARPA Funding: $1,500,000
= Total Project Cost: $1,500,000